CFTOD Asks for 3 More Years to Finish World Drive North Phase 3 Near Magic Kingdom

By WDWMAGIC Staff · Monday November 2, 2026 1:56pm ET · "Magic Kingdom"
CFTOD Asks for 3 More Years to Finish World Drive North Phase 3 Near Magic Kingdom
CFTOD wants a three-year extension for World Drive North Phase 3, pushing the deadline to December 2, 2029, with landscaping near Magic Kingdom not starting until late 2027.
Add WDWMAGIC on Google See more of our stories in Google Top Stories and Discover.

Photos / 1 in this gallery

World Drive North Phase 3 Project Area

Aerial overview map showing the World Drive Phase 3 North widening project area between Seven Seas Drive and Maple Road, with the permit modification location near Magic Kingdom marked

The Central Florida Tourism Oversight District (CFTOD) has filed for more time to finish World Drive North Phase 3, the road widening project that runs past Magic Kingdom, the Polynesian and the Grand Floridian. The current permit expires December 2, 2026. The district is asking for a three-year extension, moving the deadline to December 2, 2029.

The project has been underway for a couple of years. If you've driven to Magic Kingdom or the monorail resorts recently, you've seen the work.

The request letter, prepared by TLP Engineering Consultants for CFTOD, says construction has made significant progress, but the current deadline isn't enough to finish everything.

Here's where World Drive North Phase 3 stands, according to the filing:

  • Most utility work along the corridor is complete. The engineer calls this a significant milestone because of the amount of complex utility relocation involved.
  • Work on the final roundabout and the road surface for the last phases is underway.
  • Landscaping and area development work is expected to start in late 2027.

That landscaping timeline drives the request for three more years.

What the project covers

World Drive North Phase 3 widens World Drive from just south of Seven Seas Drive north to Maple Road. The project map shows the route running alongside the Magic Kingdom parking lot, past the Polynesian and the Grand Floridian, with roundabouts along the corridor, including one at the Grand Floridian entrance.

It connects with two other road projects:

  • World Drive Phase 2 to the south
  • The Floridian Way project to the north

A small change near Maple Road

The filing also includes a minor design change. Near where the project ties into Maple Road, the original plans called for removing 0.82 acres of existing Floridian Way pavement. CFTOD now wants to leave 0.16 acres of that pavement in place. The filing doesn't say why.

Removing that pavement was meant to offset new pavement added by the widening. Engineers say the nearby stormwater pond can still handle the runoff without changes.

Google

Conversation

529 comments
Discuss on the Forums
CFTOD Asks for 3 More Years to Finish World Drive North Phase 3 Near Magic Kingdom
CFTOD wants three more years to finish the Phase 3 road widening past Magic Kingdom, the Polynesian and the Grand Floridian, moving the permit deadline from December 2, 2026 to December 2, 2029. Most utility work is done, but landscaping won't start until late 2027, and that timeline is behind the request.

https://www.wdwmagic.com/attractions/Magic-Kingdom/news/02nov2026-cftod-asks-for-3-more-years-to-finish-world-drive-north-phase-3-near-magic-kingdom.htm
↩ replying to Smiley/OCD
yield does not mean stop for the record. they're made so the cars can fit in without having to stop; you just adjust speed. it drives me insane when people arrive and stop for the imaginary stop sign... There's one in windermere that I loathe for this reason!
↩ replying to wdwmagic
Lovely