Update on the Cinderella Castle front side refurbishment coming in January 2010

Share
We have a few more details to update the information that we posted earlier this month on the Cinderella Castle refurbishment in 2010. The refurbishment will begin on January 3 2010, beginning with draining the moat. Around January 12 2010, a construction wall scrim of around 25ft tall will be put in place (the scrim will be similar to this). The work should be done around March 25 2010, although as always, dates are subject to change. The castle will remain open and in-use as usual for the duration of the work.